The Township of Huron-Kinloss will be starting the rehabilitation of the following bridges in Lucknow:
- Ludgard St. Bridge between Stauffer St. and North Delhi St.
This project has been awarded to Lavis Construction Co. Limited. It will begin in Summer 2024. Check for updates here.
The Ludgard St. and Wheeler St. bridges will be fully closed during the rehabilitation process. All through traffic will be detoured to Gough St. or Campbell St. It is expected that the bridges will be fully closed for 4-6 weeks, weather depending.
For more information, contact the Township of Huron-Kinloss or continue to check here for updates.
Project Updates
September 23-27
Ludgard Street bridge should be re-opened by Wednesday.
September 16-20
Bridge deck waterproofing scheduled for Tuesday. Paving scheduled for Friday. - Completed
September 9-13, 2024
Bridge railing to be installed. Deck waterproofing to be done pending paving schedule. - Completed
September 3-6, 2024
Deck of bridge removed and poured concrete on deck and sidewalk. - Completed
August 6, 2024
Reconstruction of Ludgard St Bridge is scheduled for September 2024.